As we continue working to bring NELPCO members high-speed broadband internet, we will be providing regular project updates here.
Progress Report October 1, 2024
Our network covering seven parishes is complete. Construction of the Volt Broadband network across the seven-parish NELPCO footprint will be completed this month as the construction phase of the project draws to a close. The final areas to get service in...
Progress Report September 1, 2024
The final 20 miles… After completing over 1,800 miles of fiber installation in the seven-parish NELPCO footprint, only 20 miles of construction remains for the buildout of the Volt Broadband network. As we move into September, construction should wrap up in the...
Progress Report August 1, 2024
The backbone fiber buildout of the Volt Broadband network is almost complete! At this point in the two-year process, less than 40 miles remain to be constructed in the South Franklin and Como areas. This will be followed by the splicing in of all the taps which...
Project Update for Tuesday July 2, 2024
Since connecting our first customer in the early fall of 2022, there are now over 4,150 active Volt accounts with customers using the internet service daily! In addition, construction on the buildout of the Volt Broadband network is approaching the 98% mark as of the...
Progress Report for May 1, 2024
Construction on the buildout of the Volt Broadband network is right at the 90% mark as of the first of May, 2024. We are pleased to see that our take rates continue to be above 50% by NELPCO?s members taking advantage of Volt Broadband?s fiber-to-the-home initiative....
Project Update for Tuesday April 2, 2024
Project Update for Friday, March 1, 2024
Project Update for Wednesday, February 7, 2024
Project Update for Friday, January 5, 2024
Project Update for Friday, December 1, 2023
Project Update for Friday, September 1, 2023
Project Update for Friday, July 28, 2023